Northern High School Project Update

07.26.2017
WP_Term Object
(
    [term_id] => 6
    [name] => Project Updates
    [slug] => project-update
    [term_group] => 0
    [term_taxonomy_id] => 6
    [taxonomy] => news-categories
    [description] => 
    [parent] => 0
    [count] => 6
    [filter] => raw
)
Project Updates

The third story of the structural steel was recently completed at the new Northern High School Replacement project.  The upper concrete slabs at the entrance level and upper levels are poured.  The roof deck at the classroom section is nearing completion.  The structural steel is ongoing at the entrance steel is ongoing at the entrance level single story section and should be complete the end of August.  Exterior wall framing and interior CMU walls are ongoing at the classroom section, as well as mechanical, electrical, plumbing, and sprinkler above ceiling and in-wall rough in.  Site utilities are nearing completion for Phase 1 and should be complete by the end of August.